4D/5D Scheduling Overview

The 4D/5D schedule page opens in a separate browser tab from the main Conio interface. When you click the schedule link from within a project, Conio opens a dedicated scheduling workspace at the same localhost:8000 address. This separation keeps the heavy Gantt rendering isolated from the main estimating workflow, and allows you to have the schedule and the cost workspace open side by side.

The "4D" in the name refers to the time dimension added to the three-dimensional cost model: tasks placed on a CPM (Critical Path Method) timeline with durations, predecessor links, and a calculated critical path. The "5D" refers to the cost dimension layered on top of that timeline โ€” each task carries its item cost from the matched BOQ, and the schedule engine distributes that cost across the task's active working days. The result is a week-by-week or month-by-month cash-flow projection with an S-curve overlay.

The recommended workflow before opening the schedule is: import your BOQ, match rates in Scenario Studio, generate Unit Rate Analysis (URA) breakdowns for your matched items, and then synthesise the schedule. Durations are derived directly from the URA: the quantity of each BOQ item is divided by the daily output figure recorded in its URA to produce a duration in working days. Items without a URA receive a default one-day duration as a placeholder โ€” this is flagged in the schedule so you know which tasks need URA data before the programme is reliable.

Predecessor links control the sequencing of tasks on the Gantt. You can draw links manually by dragging between task bars, or use the AI Schedule feature to have the system infer construction-logical links automatically. User-set links always take priority over AI-suggested links โ€” the AI fills gaps, it does not overwrite your decisions.

Before the schedule produces meaningful output, at least one item in the scenario must have a URA with a daily output figure. A scenario with only matched rates but no URAs will produce a schedule where every task is one day long, which is not useful for programming or cash-flow forecasting. The more items with URAs, the more accurate the duration profile and the more reliable the S-curve.


What each view showsโ€‹

ViewWhat it shows
Gantt chartTask bars, durations, critical path (red), dependencies, progress
S-curveCumulative cost vs time; quality badge shows distribution score
Cash flowPeriodic spend per week or month; used to assess front-loading
Critical pathHighlighted tasks with zero float; delays here delay project completion

4D/5D schedule page showing the Gantt with linked tasks and AI Schedule button in toolbar


Next stepโ€‹